Welcome to the informational web site supporting the Environmental Impact Statement for the U.S. Navy Waterfront Projects at the Naval Base Kitsap Bangor
Commander, Naval Base Kitsap is the official sponsor of this project website. Questions regarding its content may be directed to Naval Base Kitsap Public Affairs at (360) 627-4030.
Schedule

SEIS Schedule

Notice of Intent (NOI) for SEIS published in Federal Register: March 13, 2017

Correction to the NOI for the SEIS published in Federal Register: March 21, 2017

Notice of Availability (NOA) for Draft SEIS: August 18, 2017

45-Day Public Comment Period for Draft SEIS: August 18 - October 2, 2017

NOA for Final SEIS: November 9, 2018

30-Day Waiting Period for Final SEIS: November 9 - December 9, 2018

ROD for SEIS: January 2019



FINAL EIS SCHEDULE

Notice of Availability of Final LWI and SPE EIS published in Federal Register: July 15, 2016

Public Comment Period on Final EIS: Ended on August 15, 2016

Record of Decision for the LWI proposed action published: September 14, 2016


Top of Page