Schedule

SEIS Schedule

Notice of Intent (NOI) for SEIS published in Federal Register: March 10, 2017

Notice of Availability (NOA) for Draft SEIS: August 2017

45-Day Public Comment Period for Draft SEIS: August-September 2017

NOA for Final SEIS: February 2018

30-Day Waiting Period for Final SEIS: February-March 2018

ROD for SEIS: April 2018



FINAL EIS SCHEDULE

Notice of Availability of Final LWI and SPE EIS published in Federal Register: July 15, 2016

Public Comment Period on Final EIS: Ended on August 15, 2016

Record of Decision for the LWI proposed action published: September 14, 2016


Top of Page